Geothermal Salak 7 Development Project — Steam Turbine & Generator Installation
JO Timas – Rekind
As sub-contractor, Amertec is executing the complete mechanical installation of a 45.3 MW Steam Turbine & Generator unit (Fuji Electric) at GPP AWI-1, Star Energy Geothermal Salak — from sole plate setting and turbine erection through to commissioning readiness.